Some projects are already time-bound when you receive them, and while this way of planning is not the most controlled way to manage a project, it is possible – and I am just about to find out how possible. Suddenly, a project that has been dragging on for a year, and I thought I had killed, now has to be delivered by 21 April. Just like that. So I have to link one of our intranets to the phone system, manage the phone service provider, an infrastructure contractor, a developement consultancy and France Telecom’s involvement. And I thought it was going to be a slow week.
I’ve interviewed the owner of Bridal Blossoms this week about this very subject, and Stephanie was insightful about how to plan to a fixed date: wedding dates are chosen to be convient to the bride and groom and not because it takes six months to plan the event, so I thought talking to people involved in the wedding business would give me some ideas of best practice for planning to a fixed date, and it has.
Projects with fixed end dates present a different type of planning challenge for project managers. Instead of being able to analyse and plan, you are told what to do and when to do it by. The analysis part of planning has to take on a different spin when your implementation time is already ticking away.
Whatever the reason for the time constraint, the planning approach for time-bound projects should start off in exactly the same way as for those without time constraints. Work out the end date ignoring the fixed delivery date, even if you do have to crash your analysis time into a shorter period and use estimates with a greater degree of uncertainty than normal. If your schedule shows that you can deliver before the expected date, that’s great. If not, move into proactive planning mode and get creative to find a way to deliver on time.
It is rarely impossible to deliver on time, given the right amount of resources, an unlimited budget and a tightly controlled project scope, but projects seldom meet these criteria. With fixed date projects:
- plan creatively to slash time out of the schedule, and
- get the support of your sponsor for when you have to steamroller through the office bureaucracy.
An update on those licences – they were extended until the end of the week and now the service has been suspended until the procurement process to buy ‘proper’ ones is finished. So we’re not booking any more online meetings. And my glove was never handed in…
If you liked this, you might enjoy:
- Fixed date projects: more advice from the experts Last week we saw that PRINCE2 doesn’t really have much advice to offer the project manager stuck with delivering to a fixed date. I also...
- Inside PRINCE2: Fixed date projects Planning is an essential part of what project managers do, so you would expect there to be some mention of how to deal with fixed...
- Expert advice on fixed date projects As part of this month’s focus on managing projects with fixed dates, I asked J. LeRoy Ward, PMP, PgMP, Executive Vice President Product Strategy &...
Follow me on Twitter


Pingback: Fixed Date Feb & ThePlanIs.com | A Girl's Guide to Project Management